Solution blueprint

Data center to Azure, in waves

The migration itself is the easy half. The half that decides whether you are better off afterwards is the landing zone, the identity design and who operates it on Monday.

The situation

A company has a data center lease ending and wants to move to Azure rather than renew. The estate is mixed: domain-joined Windows servers, a few Linux application servers, two SQL Server databases, a file share everyone uses and several applications nobody has documented.

The deadline is real, which is useful, and dangerous: it tempts teams to lift and shift everything quickly into a single subscription with no governance, and inherit a worse version of the same problem. This blueprint builds the foundation first and then moves in waves.

Constraints that shape the plan

  • A fixed lease end date, so the plan has to fit a calendar.
  • Applications with unknown dependencies, discovered rather than documented.
  • An existing on-premises Active Directory that applications depend on.
  • No agreed address plan, and overlapping ranges in test environments.
  • A team that has to run the result, so simplicity beats elegance.
  • Recovery expectations that have never been written down or tested.

Landing zone, conceptually

Management

  • Management group hierarchy
  • Azure Policy for guardrails
  • Subscription per environment
  • Tagging standard
  • Budgets and cost alerts

Set before workloads arrive. Retrofitting governance onto running systems is the expensive path.

Identity

  • Entra ID with conditional access
  • Privileged Identity Management for admin roles
  • Managed identities for workloads
  • Domain services or extended Active Directory for domain-joined servers

Decide early how domain-joined applications authenticate in the cloud.

Network

  • Hub virtual network with shared services
  • Spoke per workload or environment
  • VPN or ExpressRoute to the data center during migration
  • Private endpoints for platform services
  • Centralized egress and inspection if policy requires

The address plan has to cover on premises, cloud and future growth before the first subnet is created.

Platform

  • Log Analytics workspace
  • Defender for Cloud
  • Backup and recovery vaults
  • Key Vault for secrets
  • Infrastructure as code in version control

Logging and backup are part of the foundation, not a later project.

A conceptual landing zone. The specifics depend on your regulatory needs, size and operating model.

The approach, phase by phase

Phase 1: Discover and assess

Four to six weeks.

  1. 1

    Inventory with tooling

    Agent-based and agentless discovery for servers, with performance data over a full business cycle.

  2. 2

    Map dependencies

    Network flow data to find the connections nobody documented, then confirm with application owners.

  3. 3

    Classify each workload

    Rehost, replatform, refactor, replace with software as a service, or retire. Retiring things is real progress.

  4. 4

    Capture requirements

    Availability, recovery time and point objectives, data residency, compliance and licensing.

  5. 5

    Wave plan

    Group workloads so each wave is independently testable and reversible.

Phase 2: Build the foundation

Four to eight weeks.

  1. 6

    Landing zone

    Management groups, subscriptions, policy, tagging, budgets, in code.

  2. 7

    Network

    Address plan, hub and spokes, connectivity to the data center, name resolution.

  3. 8

    Identity

    Conditional access, privileged role management, the approach for domain-joined servers.

  4. 9

    Observability and backup

    Log collection, alerting, backup policies and a tested restore.

  5. 10

    Pilot wave

    Two or three low-risk workloads end to end, to prove the foundation and the runbook.

Phase 3: Migrate in waves

Ongoing, wave by wave.

  1. 11

    Prepare each wave

    Owner sign-off, test plan, cutover window, rollback and a communication plan.

  2. 12

    Replicate and test

    Replicate, bring up a test copy, let the application owner verify it, fix what breaks.

  3. 13

    Cut over

    In the agreed window, with a checklist and a decision point for rollback.

  4. 14

    Validate

    Function, performance, connectivity, backup, monitoring and cost, for each wave.

  5. 15

    Decommission

    Only after an agreed quiet period, with backups retained to policy.

Phase 4: Operate and optimize

From the first wave onward.

  1. 16

    Operations handover

    Runbooks, alert ownership, escalation paths and on-call arrangements.

  2. 17

    Recovery testing

    Test the recovery plan rather than documenting it. Record the results.

  3. 18

    Cost management

    Rightsizing, reservations or savings plans where usage is stable, and a monthly review with an owner.

  4. 19

    Security posture

    Act on Defender for Cloud findings, close the gaps and set a review cadence.

  5. 20

    Modernization backlog

    Replatform the workloads that were rehosted to meet the deadline, now on your own schedule.

Phase names and order change with the engagement. This is a typical shape, not a fixed method you would be held to.

The kind of team this needs

Platform

  • Cloud architect
  • Network engineer
  • Identity engineer
  • Infrastructure as code engineer

Migration

  • Migration engineers
  • Database engineer
  • Application owners from the business
  • Test coordinator

Operations and security

  • Site reliability or operations engineer
  • Security engineer
  • Cost and licensing analyst

Roles can be ours, yours or shared. Where you only need people rather than a project owner, the same roles are available through staffing.

Typical deliverables

  • Workload inventory with dependencies and performance data
  • Migration strategy per workload, including what is retired
  • Landing zone design and the code that builds it
  • Address plan and network design
  • Identity and privileged access design
  • Wave plan with cutover and rollback runbooks
  • Backup, recovery and monitoring design with a tested restore
  • Operations handover pack and runbooks
  • Cost baseline and optimization plan

What usually goes wrong, and what we do about it

  • Unknown dependencies

    Found with flow data in discovery, not during a cutover weekend.

  • Lift and shift into one subscription

    The foundation phase exists precisely to stop this, and it is built in code so it can be changed.

  • Address overlaps

    The address plan covers cloud, on premises and growth before anything is deployed.

  • Nobody can operate it

    Operations handover is a deliverable with runbooks and named owners, and we train your team as the waves run.

  • Cost surprises

    A baseline, budgets and alerts from day one, and a monthly review with an owner rather than a quarterly shock.

  • Recovery assumed rather than tested

    We test a restore in the foundation phase and again after the first production wave.

Questions people ask

Can we move everything as-is to meet the deadline?

Often yes for most workloads, and that is a legitimate choice when a lease is ending. Classify the exceptions honestly and keep a modernization backlog instead of pretending the move finished the job.

Do we still need Active Directory?

Usually, for a while. Domain-joined applications need a plan: extend the domain, use a managed directory service, or modernize the application. This gets decided in phase one.

Does this work for AWS or Google Cloud?

The shape is the same: foundation, then waves. The services differ. See the cloud migration planner and our AWS landing zone article.

Can you operate it for us afterwards?

Only under a written agreement that says what we are responsible for and when. We do not advertise around-the-clock operations we have not contracted for.